Stavian Group says its planned Stavian Digital Park in Ho Chi Minh City could cover 300 hectares, with 300 MW in a first phase by 2030. TechNode Global reported the figures on September 25.
Cushman & Wakefield will lead a feasibility study funded by a grant from the U.S. Trade and Development Agency. APTelecom will plan connectivity, market development and commercialization. The study has 15 workstreams and will produce a master plan, financial model and procurement framework.
Stavian also cites access to international subsea connectivity of up to 200 Tb per second. The proposed carrier neutral campus would serve cloud providers, enterprises, public systems and AI workloads, with on site solar and other renewable energy planned.
These are project targets, not secured capacity or a construction commitment. The study must test power, cooling, site suitability, financing and demand before operators can treat the campus as available supply.
The-Delta's Takes Editorial Analysis
What This Means
Stavian has now put numbers and a target year on the campus proposal. The earlier Delta report on the USTDA funded study said capacity and delivery timing had not been disclosed. The new 300 MW first phase target and 2030 goal make the project easier to compare with Vietnam's wider data centre pipeline, while the 200 Tb per second connectivity figure signals an ambition to serve international workloads.
For cloud and AI operators, the proposal could eventually add carrier neutral capacity in Ho Chi Minh City. The key distinction is that these are planned specifications inside a feasibility study, not power already allocated or a facility ready for customer workloads.
Execution Reality Medium
The study covers 15 workstreams, including power, cooling, connectivity, financial viability, sustainability, regulation and implementation. No construction start, project cost, secured power allocation or customer commitment is disclosed. The stated capacity and connectivity therefore remain targets pending a bankable plan and procurement decisions.
The Signal
Watch whether the study identifies a secured power source, financing plan and anchor customers for the 300 MW first phase. A procurement framework or named operator would show whether the 2030 target is moving beyond a planning assumption.