Stavian Group says its planned Stavian Digital Park in Ho Chi Minh City could cover 300 hectares, with 300 MW in a first phase by 2030. TechNode Global reported the figures on September 25.

Cushman & Wakefield will lead a feasibility study funded by a grant from the U.S. Trade and Development Agency. APTelecom will plan connectivity, market development and commercialization. The study has 15 workstreams and will produce a master plan, financial model and procurement framework.

Stavian also cites access to international subsea connectivity of up to 200 Tb per second. The proposed carrier neutral campus would serve cloud providers, enterprises, public systems and AI workloads, with on site solar and other renewable energy planned.

These are project targets, not secured capacity or a construction commitment. The study must test power, cooling, site suitability, financing and demand before operators can treat the campus as available supply.