tag#shtp
3 articles
Genbyte Technology signed a VND271.04 billion engineering and construction contract with FANCONS for an electronics plant in Saigon High-Tech Park, disclosed to the Shenzhen exchange on 13 November with 420 days of build time.
Ho Chi Minh City needs roughly 6,000 MW of additional capacity to keep production running to 2030, with peak demand forecast to rise from 9,471 MW to 16,103 MW while data centres and semiconductor plants add load outside Saigon High Tech Park.
Municipal directive orders Saigon Hi-Tech Park to cut administrative procedure timelines in half compared to 2024, mandate automated digital screening, and decentralize land allocation approvals before 25 October 2026.