Ho Chi Minh City needs about 6,000 MW of additional capacity to meet production demand to 2030, according to calculations by the municipal Department of Industry and Trade. The city consumes about 58 billion kWh a year with peak demand near 9,471 MW. By 2030 the forecast is 93.972 billion kWh and a peak of about 16,103 MW, Vietnam News Agency reported.
The park level number is the one The-Delta covered on 14 November: at least 693 MVA of transformer capacity across 5 new 110 kV substations at Saigon High Tech Park between 2025 and 2030, 4 of them inside the 913 hectare park at 504 MVA and 1 at 189 MVA in the 194.84 hectare expansion. The 6,000 MW is a different unit for a wider boundary, covering industrial and export processing zones where the report says data centre load is now spreading.
The rule changed on 22 September 2026, when the People's Council adopted Resolution 47/2026 and added LNG fired generators and consumers in industrial parks, export processing zones, economic zones, industrial clusters and hi tech parks to direct power trading through dedicated connection lines. That widens who can contract supply outside the state utility tariff, which is the mechanism a data centre needs before it commits capacity.
Supply additions remain in planning. The city intends a national energy centre in the Ba Ria and Vung Tau area to supply the city including its data centres. Pacifico Energy Vietnam received approval from the Ministry of Agriculture and Environment in 2026 to survey sea areas for 2 offshore wind projects, 1 of them 500 MW off the city at an estimated 2 billion USD. Neither carries a delivery date in the report.