Vietnam will probably miss a 2027 target for the first trial production run at its first semiconductor plant, Reuters reported on 26 October 2026, citing a person with direct knowledge of the project and 3 people familiar with talks to buy ASML equipment. A Reuters visit last week found the site outside Hanoi covered in wild vegetation, and satellite images from Planet Labs in January and Airbus in October show no buildings constructed.
The delay traces to 2 named causes, Viettel's lack of experience building chip factories and administrative hurdles in securing government funding. Viettel broke ground in January and said then that it wanted the plant fully operational by 2030, supplying chips to aerospace, telecom and auto customers. Authorities put the cost at about 1.3 billion USD. Viettel told Reuters the project was progressing in line with the established plan and schedule, with activities carried out in phases.
The equipment question is unresolved. Talks with ASML have run for months over a DUV lithography machine, which prints circuit patterns onto silicon wafers, according to 3 people familiar with the discussions. Reuters could not establish why no agreement was reached or which DUV model was under discussion, and the model decides whether Dutch export controls apply and what the machine costs. ASML declined to comment.
The gap matters because Vietnam's semiconductor position sits in assembly, testing and packaging, not fabrication. Intel, Amkor Technology and Hana Micron run large ATP plants in the country, and The-Delta.io reported on 5 October that Samsung Electronics plans a memory testing line in Thai Nguyen for Q4 2027. Those operations test wafers fabricated elsewhere. A working Hanoi fab would be the first domestic step into front end production, and the party's plan for high income status by 2045 leans on it.
The open question is what replaces the 2027 date. Neither Viettel nor the finance ministry has published a revised timeline, ASML said this month it may not fully meet demand for its most advanced machines over the next 2 years, and the project still needs a signed equipment contract, a funding route and a construction start before any trial wafer runs.