Vietnam could face a capacity shortfall of 4,256 MW and 2.9 billion kWh of electricity in 2027 as demand from data centres, AI facilities, semiconductor manufacturing and electrified transport accelerates, the Ministry of Industry and Trade warned in a report carried by Vietnam News.
The projected shortage grows to 20.7 billion kWh in 2028, 50.4 billion kWh in 2029 and around 61 billion kWh in 2030. The ministry flagged the northern region as the most exposed, where industrial expansion and new high demand projects concentrate faster than generation and transmission can follow.
Delivery is the core problem. After roughly 3 years of implementing the revised Power Development Plan VIII, only about 5% of planned generation capacity has entered operation. About 9% is under construction, 28% has selected investors without breaking ground and 45% has not received investment approval. Of 43 major transmission projects scheduled for 2026 to 2030, only 10 have entered construction.
The ministry proposed around 2,800 MW of state funded rooftop solar at hospitals, schools and government offices completed before June 2027, plus 3,000 to 5,000 MW of industrial rooftop solar paired with storage before the 2027 and 2028 dry seasons, and 2 to 3 GW of batteries to cover peak hours.
For the longer term, the ministry wants the plan adjusted to allow additional coal fired generation to compensate for delayed baseload capacity. LNG projects remain blocked by fuel prices, financing and power purchase agreement negotiations, while the revived Ninh Thuan 1 and 2 nuclear projects still lack an implementation timetable.
The-Delta's Takes Editorial Analysis
What This Means
For data centre operators, semiconductor investors and industrial tenants, the report makes power availability a primary site selection criterion. A large AI facility can draw hundreds of MW at a single location around the clock, and the report shows the national plan was not built for that load profile arriving this fast.
The mitigation package points to where the state will act first: public buildings, industrial clusters and storage. Operators planning facilities in northern Vietnam should verify grid connection timelines and backup options rather than relying on planned capacity figures.
Rising power risk also feeds into electricity pricing. Experts cited in the report say prices are not yet attractive enough for investors in generation, which suggests tariffs or support mechanisms will have to move before private capital fills the gap.
Execution Reality High
Only 5% of planned generation capacity is operating after 3 years, and the mitigation measures are proposals rather than approved programmes. The rooftop solar targets, battery additions and 1 GW of new generation in 2027 all require funding decisions, procurement and installation within months.
The 2,800 MW state funded rooftop solar programme must complete before June 2027 to affect the first projected shortfall. Any delay pushes the 2027 gap directly into the dry season.
The Signal
Watch the revised Power Development Plan VIII. Its treatment of coal, renewables and the demand forecast will show whether the government accepts the shortfall numbers or rebases the plan around them.
The first hard test is the June 2027 rooftop solar deadline. Funding allocated and installation started well before that date would indicate the quick fix is real. The second is whether the 2027 dry season produces rationing or blackout events in the north.
For the AI infrastructure story, the signal is siting. If new data centre announcements cluster where transmission is already strong, operators are pricing the shortage in.