Vietnam could face a capacity shortfall of 4,256 MW and 2.9 billion kWh of electricity in 2027 as demand from data centres, AI facilities, semiconductor manufacturing and electrified transport accelerates, the Ministry of Industry and Trade warned in a report carried by Vietnam News.

The projected shortage grows to 20.7 billion kWh in 2028, 50.4 billion kWh in 2029 and around 61 billion kWh in 2030. The ministry flagged the northern region as the most exposed, where industrial expansion and new high demand projects concentrate faster than generation and transmission can follow.

Delivery is the core problem. After roughly 3 years of implementing the revised Power Development Plan VIII, only about 5% of planned generation capacity has entered operation. About 9% is under construction, 28% has selected investors without breaking ground and 45% has not received investment approval. Of 43 major transmission projects scheduled for 2026 to 2030, only 10 have entered construction.

The ministry proposed around 2,800 MW of state funded rooftop solar at hospitals, schools and government offices completed before June 2027, plus 3,000 to 5,000 MW of industrial rooftop solar paired with storage before the 2027 and 2028 dry seasons, and 2 to 3 GW of batteries to cover peak hours.

For the longer term, the ministry wants the plan adjusted to allow additional coal fired generation to compensate for delayed baseload capacity. LNG projects remain blocked by fuel prices, financing and power purchase agreement negotiations, while the revived Ninh Thuan 1 and 2 nuclear projects still lack an implementation timetable.