Long Hau Joint Stock Company approved a VND 1,500 billion borrowing limit with BIDV's Ho Chi Minh City branch on 27 October, over 84 months, to fund infrastructure on the 90 hectare phase 2 expansion in Can Giuoc, Tay Ninh province. The board resolution follows a shareholder plan set in April.

The project totals VND 3,158 billion including VAT, split between VND 480 billion of equity, the VND 1,500 billion facility and about VND 1,178 billion from operating cash flow. That number has moved. The 2021 proposal carried a VND 2,592 billion estimate, and the increase of VND 566.3 billion, or 21.8%, comes mostly from land clearance and resettlement costs plus a sharper rise in construction materials, sand for leveling above all.

The timing explains the borrowing. The Ben Luc to Long Thanh expressway opened along its full 57.8 km in early October, putting the park at the Nguyen Van Tao interchange and next to the Hiep Phuoc seaport complex. Registered FDI reached over $50.36 billion in the first 9 months of 2026, with $21.07 billion disbursed, the highest in 5 years and over 82% of it into processing and manufacturing. Southern industrial land supply exceeds 36,000 hectares, and average occupancy already stands at 76.3%.

Long Hau's own parks show the squeeze. Phases 1 and 2 are fully occupied and phase 3 is at 64%, with the company expecting the remaining space to go by the end of 2027. The expansion adds roughly 66.6 hectares of leasable industrial land, handed over in 3 phases of about 30 hectares each, with the first plots from Q4 2027.

The open question is whether the 21.8% cost increase is the end of the repricing. Land clearance and material costs are the 2 inputs least responsive to a company's own execution, and an 84 month facility is long enough to absorb a further round without breaking the structure. Whether the park can hand over on schedule while holding its stated refusal to fill space at any cost is what a phase 3 occupancy figure will eventually show.