Can Tho has established a 200 hectare technology park in O Mon ward under Decision 4902/QD-UBND, with 100 more hectares reserved for possible expansion. TechNode Global reports planned investment above VND 5 trillion, about $192.4 million. The site is intended to serve the Mekong Delta with research, production, training and business incubation.

The funding plan allocates nearly VND 1.44 trillion to the city and about VND 3.61 trillion, or 71.54%, to sources outside the state budget. Those sources may include foreign investors, development assistance, infrastructure developers and future tenants. TechNode Global names no committed private investor or lender for that share.

Of the initial area, 94.8 hectares are designated for technology production and 31.6 hectares for research, training and incubation. Priority fields include biotechnology, automation, new materials, energy and technologies for processing agricultural goods.

The 2026 to 2028 phase covers legal work, a management board, detailed planning, land clearance and the start of infrastructure construction. Infrastructure is planned for completion from 2028 to 2030, with full operation expected after 2030. These are planned milestones rather than completed facilities.